Work continues in the clubhouse and new gym, it is projected to be completed in July depending on any construction delays.
The following is in progress with construction:
- Installation of the additional 14 windows is under way; this will take longer than anticipated due to dry-rot damage and extent of stucco removed;
- The floor has been installed in the new gym and clubhouse;
- The appliances have been installed in the kitchen;
- Interior sanding and staining of the new wood ceilings; and
- Replaced the interior and exterior perimeter doors of the clubhouse, new gym and restrooms.
Please keep an eye on the website for updates and the grand opening celebration.